Repair work is continuing on the railway in Wickford with engineers working "night and day" after a train derailed last week.
On August 14, a Greater Anglia train came off the track south of Wickford station at 2.12pm, with more than 60 passengers on board.
No injuries were reported, but the incident has caused significant disruption and damage.
Crews working at the scene on Friday (Image: Lucy North / PA Wire)
In an update today, a spokesman for Greater Anglia said: "We continue to work night and day to repair the railway in the Wickford area following last Friday's derailment.
"Yesterday saw further progress as we started to see some of the key materials arriving at the site by rail, after the removal of the train involved the day before.
"This meant that supplies of the some of the sections of replacement rails, and the ballast that supports the track, could begin to be delivered."
Read more
-
Major update issued amid Greater Anglia disruption after train derailed
-
Busy commuter road to remain closed all week after train derailment
-
Roadworks across south Essex causing disruption as pipes leak during dry weather
Closed - Salcott Crescent remains shut off both ways (Image: Newsquest)
Repairs include more than one and a half miles of track, over 3,700 sleepers, and work to restore signalling and overhead line equipment.
Greater Anglia has described the repairs as a "huge and complex task" and says that process is still expected to take another week.
The spokesman added: "We're doing all we can to complete those repairs and restore a normal service as soon as possible.
"As soon as we can confirm a date for re-opening of the railway and reintroduction of the normal service, we will do so."
Salcott Crescent remains closed in both directions from Pebmarsh Drive to Foxhatch.